Chapter Two
Trial sites
2.1
This chapter provides an update on the progress of the National
Disability Insurance Scheme (NDIS) trial sites. It collates data and outcomes from
both the National Disability Insurance Agency (NDIA) and the Western Australian
Disability Services Commission (DSC) managed trial sites.
Highlights of the trial sites
2.2
As of 30 June 2015, both the above organisations managing NDIS trial
sites, reported that 22 936 requests for access had been lodged by people with
disabilities to become participants in the NDIS.[1]
Of these people, 20 322 were found to be eligible, which equates to approximately
90 per cent of all access requests, and
1674 were found ineligible. In addition, 17 991 participant plans were approved
across the trial sites.[2]
This approval rate represents a 90 per cent achievement against the 30 June
2015 cumulative bilateral target for participants with approved plans.
2.3
Furthermore, NDIA managed a 94 per cent achievement against the
bilateral agreements for its trial sites with 17 303 active participants receiving
approved plans.
2.4
The NDIA reports that 'the most common funded supports in dollar terms in
its plans are daily tasks in shared living arrangements, community
participation, and assistance with personal activities. The most commonly
funded support in South Australia, however, is early childhood support.'[3]
2.5
The NDIA notes that 'overall, $952.8 million has been committed for
participant support costs'. From these funds NSW and Victoria received the
lion's share at $343.6 million for NSW and $295.5 for Victoria. South
Australia received $111 million, Tasmania $93 million, ACT $64.6 million, Perth
Hills $41.2 million and $3 million went to the Northern Territory. The My Way
trial reported committing $17.9 million in plan supports for the financial year
for participants in the Lower South West trial site.
2.6
The average annualised package cost across for NDIA managed trial sites
is $33 600 once the large residential centres of Stockton and Colanda are excluded.
Not to be compared, the WA My Way cost was $26 014 (funded and no funding
requested) noting that the WA government provides some services at no cost.[4]
The planned roll-out
2.7
The 17 April 2015 COAG communiqué originally envisaged that the new
round of bilateral agreements for the transition to the full scheme would be
agreed in July-August 2015.[5]
However, as the Assistant Minister for Social Services, Senator the Hon Mitch
Fifield informed the Senate on 18 August 2015, he was still in negotiations
with the states and territories on the bilateral agreements.
2.8
The first four trial sites that began operations from 1 July 2013— the
Hunter in New South Wales, the Barwon region in Victoria, Tasmania and South
Australia, (as listed in Table 2.1)—continued to grow and thrive throughout
2014–15. Since 1 July 2014 three more trial sites commenced operations.
2.9
As of 1 July 2014, four more sites commenced operations. The Australian
Capital Territory (ACT), which is a full territory-wide operation across all
age groups—so is effectively already progressing through transition, the Barkly
trial site in Northern Territory, while expansive geographically—is centred on
the Tennant Creek area, and in Western Australia there are two sites—the NDIA-run
NDIS Perth Hills trial site and the WA Disability Services Commission run NDIS
My Way trial site in the Lower South West region of the state.
2.10
The planned roll-out of the NDIS is shown in Table 2.1. From 1 July 2016
most trials sites will progress into the 'general transition period' before full
scheme.
Table 2.1: Planned NDIS roll-out
The trial sites
2.11
The trial sites now number eight in total—the locations are:
-
The Hunter trial site – Newcastle, Lake Macquarie, and Maitland Local Government Areas (LGAs) in New South Wales.
-
The Barwon trial site – Greater
Geelong, Surf Coast, Queenscliff and Colac-Otway LGAs in Victoria.
-
The South Australian
trial site – 0-14 year olds.
-
The Tasmanian trial
site – 15-24 year olds.
-
The Australian Capital Territory
site.
-
Busselton, Lower South West Region of Western Australia.
-
The Perth Hills trial
site - Swan, Kalamunda and Mundaring LGAs in Western Australia.
-
The Barkly region trial site
in the Northern Territory.
Additional trial sites
2.12
Throughout the year there have been discussions at the Council of
Australian Governments (COAG) about additional trial sites. The 17 April 2015 COAG
communiqué stated that both Queensland and the Northern Territory had agreed
with the Commonwealth to discuss new trial sites. [6]
The NDIA had previously noted that the NDIS would eventually support 97 000
Queenslanders once it is roll out across Queensland over a three-year period
from 1 July 2016. [7]
2.13
On 25 September 2015, the Prime Minister, the Hon Malcom Turnbull MP and
the Queensland Premier, the Hon Annastacia Palaszczuk MP jointly announced a
Queensland trial for young people under 18 in Townsville, Charters Towers and
Palm Island commencing in early 2016.[8]
2.14
The committee also notes that the Commonwealth Government allocated
additional funding in the 2015-16 Budget to start delivering early intervention
services for up to 2 000 children under the age of 18 in Western Sydney from 1
July 2015.[9]
2.15
Hon. John Ajaka MLC, NSW Minister for Disability Services announced the
launch of Western Sydney trial site on 1 July 2015 for the Nepean, Blue
Mountains and Hawkesbury region.[10]
The second part of the WA NDIS My Way trial commenced in the Cockburn-Kwinana
region south of Perth from 1 July 2015.
Committee visits and public
hearings
2.16
Since the establishment of NDIS trial sites, the committee has endeavoured
to visit all trials sites. During the last twelve months the committee visited,
and in most cases undertook hearings, in each of the new trials sites that
commenced operations from 1 July 2014, as well as Queensland. The committee
held visits or hearings in:
-
Brisbane on 13 March;
-
Canberra on 27 March;
-
Busselton, Western Australia on 8 April;
-
Perth Hills, Western Australia on 9 April;
-
Visited the Tennant Creek community in the Northern Territory;
and
-
Darwin, Northern Territory on 21 July.
2.17
Early in the year the committee undertook a hearing in Brisbane to take
evidence from service providers regarding their readiness to transition into
the Scheme. In March 2015, the Committee held a hearing into the ACT trial
site where it heard from participants, family members, carers, service
providers and the ACT Government and NDIA officials. In the afternoon, the
committee conducted a roundtable hearing into advocacy from the following
organisations:
-
Disability Advocacy Network of Australia (DANA);
-
A.C.T. Disability, Aged and Carer Advocacy Service (ADACAS);
-
Disability Advocacy NSW;
-
Advocacy Tasmania Inc;
-
JFA Purpleorange (South Australia);
-
Disability Advocacy and Information Service Inc;
-
Our Voice (Inclusion Australia); and
-
Australian Cross Disability Alliance (ACDA). ACDA organisations members
are:
- Children with Disability Australia (CDA)
-
First Peoples Disability Network Australia (FPDN)
- National Ethnic Disability Alliance (NEDA)
-
People with Disability Australia (PWDA)
-
Women With Disabilities Australia (WWDA)
2.18
In April 2015, the committee visited both Western Australian trials
sites undertaking hearings at each. And finally, in July 2015, members of the
committee visited Tennant Creek and the NDIA Barkly trial site office where
they met with participants, family members and carers, and the local NDIA
staff. The committee members also met with representatives of the Anyinginyi
Health Aboriginal Corporation and the Julalikari Council Aboriginal Corporation.
2.19
The committee found these meeting extremely useful and would like to extend
its thanks and appreciation to all those it met during its visit to Tennant
Creek.
2.20
The following day, 21 July 2015, the committee met in Darwin and undertook
a hearing to take evidence on the Barkley trial site from service providers and
community organisations. The committee also took evidence from the Northern
Territory Minister for Disability Services, the Hon John Elferink MLA.
2.21
The committee would like to thank all those who attended the hearings.
Progress in the trial sites
2.22
The committee understands that all trial sites are progressing well with
participant satisfaction rates high to very high in NDIA run trial sites. Encouragingly,
the transition of participants is advancing well and in many cases meeting
bilateral targets for 30 June 2015. Indicative average individual package costs,
when large residential facilities are taken out of the cost calculation show
that the average annualised package cost is remaining generally under the
bilateral target price. The range of supports is developing, especially as
market opportunities arise with more providers registering. The Agency's capacity
and ability has also improved, providing more assistance for participants
transitioning into the scheme.
Participant satisfaction
2.23
The committee notes that the NDIA's survey methodology was the subject
of recommendation nine in last year's report. The process described in the
eighth quarterly report[11]
provides greater confidence in the satisfaction rating as the survey results
are now collected after the planning process by someone other than the
planner. The NDIA annual report notes that 'Participant satisfaction remains
high':
Of the 1644 participants satisfaction with the Agency has
remained very high in recent months. Satisfaction is reported on a scale of
very poor (-2) to very good (+2), with neutral being 0. The participant
satisfaction level is currently 1.63, consistent with the March results.[12]
2.24
The WA NDIS My Way scheme quarterly report, mentions a number of
independent surveys it has undertaken and has apparently found high levels of
satisfaction with the My Way service and the My Way Coordinator role:
[A]n external consultant (Patterson’s Research Group)
conducted an independent consumer satisfaction survey to gain insight into how
the WA NDIS My Way model is working for people with disability, their families
and carers. Again, the survey results indicate high satisfaction levels across
fundamental areas including the planning process, My Way Coordinator role,
access to supports and services and inclusion in the general community.[13]
Participants—numbers and access
2.25
The committee notes that presently, there are a total of 19 885 active
and inactive participants in both the NDIA-run trials sites and the WA NDIS My
Way sites. Of these, 17 991 participants have received an approved plan. The NDIA
note that of its 17 303 approved plans, 4 per cent are Aboriginal or Torres
Strait Islanders (ATSI) and another 4 per cent come from Culturally and
Linguistically Diverse (CALD) backgrounds. However, the number of Indigenous
participants is fewer than expected overall. The NDIA surmise that this is due
to under reporting of Indigenous status in the NDIA's early application
records.[14]
Table 2.2: Key statistics of all NDIS trial sites – as of 30 June 2015
Measure
|
Hunter (NSW)
|
SA
|
Tas
|
Barwon
(Vic)
|
ACT
|
Barkly (NT)
|
Perth Hills
|
MyWay (WA)
|
Total
|
Average annualised cost of packages for
Q4 2014-15 ($)
|
38,973
|
18,234
|
56,940
|
35,317
|
45,361
|
50,327
|
34,894
|
26,014
|
306,060
|
Number of participants in bilateral
agreement
|
5,030
|
4,688
|
960
|
4,521
|
1,537
|
103
|
1,642
|
1,404
|
19,885
|
Access requests
|
5,965
|
6,068
|
1,175
|
5,386
|
2,314
|
79
|
1,576
|
373^
|
22,936
|
Accepted as eligible
|
4,829
|
5,506
|
1,053
|
4,656
|
2,037
|
68
|
1,396
|
777
|
20,322
|
Percentage deemed eligible compared with
expected
|
99%
|
118%
|
119%
|
105%
|
133%
|
45%
|
85%
|
55%
|
102%
|
Number of participants with approved
plans
|
4,605
|
4,660
|
959
|
4,392
|
1,427
|
61
|
1,199
|
688
|
17,991
|
Percentage with approved plans compared
to expected
|
92%
|
99%
|
106%
|
97%
|
93%
|
41%
|
73%
|
49%
|
90%
|
Ineligible
|
670
|
349
|
43
|
350
|
143
|
6
|
106
|
7
|
1,674
|
Other
|
466
|
213
|
79
|
380
|
134
|
5
|
74
|
n/a
|
1,351
|
Average days from access request to plan
approval+
|
89
|
128
|
115
|
90
|
58
|
36
|
31
|
53
|
n/a
|
Review of decisions (internal)
|
77
|
50
|
4
|
129
|
31
|
0
|
11
|
0
|
302
|
Participants accessing mainstream
services
|
81%
|
88%
|
73%
|
86%
|
87%
|
82%
|
66%
|
n/a*
|
n/a
|
Source: National Disability
Insurance Agency, Report on the sustainability of the scheme, I July
2013 – 30 June 2015, July 2015, p. 3. Disability Services Commission, Quarterly
Report to the Commonwealth Government, 1 April 2015 to 30 June 2015 (fourth
quarterly report), p. 6. *Participants access to mainstream services does not appear as a disaggregated
measure in the WA My Way quarterly
reports. ^MyWay transferred individuals directly into the scheme on 1 July 2014;
this figure represents those who have requested access since the scheme began, p.
22 of the DSC 30 June 2015 Quarterly Report. +The
data for Average days from access request to plan approval is from the
31 March 2015 NDIA quarterly report; this data was not provided in the 30 June 2015quarterly
report.
2.26
WA My Way has a similar participation rate of ATSI as the NDIA, while
its CALD representation is only just above 1 per cent.[15]
2.27
Table 2.2 also presents the participant statistics across all trial sites
at
30 June 2015. It shows the bilateral numbers agreed between the Commonwealth
and the respective governments for the anticipated number of participants entering
the Scheme and the number of participants that actually receive an approved
plan.
2.28
The table shows the cumulative percentile measure of Percentage with
approved plans compared to expected that indicates a 90 per cent
achievement for plans approved against the cumulative [NDIA and My Way trial
sites] bilateral agreement number of 19 885 at this point in time.
Individually, the NDIA managed 94 per cent against its collective target—a
commendable achievement for the Agency.
2.29
On these measures, the Tasmanian trial site recorded the highest
percentile intake exceeding its bilateral target of participants with approved
plans by reaching 106 per cent. These results were followed by South Australia
at 99 per cent and then Barwon, Victoria on 97 per cent.
2.30
The committee notes that while most of the sites are on track to reach
their bilateral targets of 'Number of participants with approved plans',
a number have actually exceeded the other bilateral measure of 'Percentage
deemed eligible compared with expected'. This measure captures the number
of participants that have been assessed as being eligible to enter the Scheme.
For example, the ACT has assessed and found over 133 per cent of participants
eligible against the point in-time bilateral agreed intake, likewise Tasmania
is at 119 per cent and South Australia at 118 per cent. Though in both the
South Australian and Tasmanian data, it is evident that while participants are
processed as 'eligible' quickly, the data shows that they have the long wait
times of 115-128 days until an approved plan is finalised.
2.31
Other prominent issues include: 1) the Western Australia trial sites
lower than expected results in approving plans or eligibility—Perth Hills at 73
per cent of its bilateral target and My Way at 49 per cent of its target; and
2) The Northern Territory's low number of plan approvals at 41 per cent highlights
the significant challenge of trying to deliver such a significant social reform
across Australia particularly in rural and remote locations.
Participant outcomes
2.32
This section provides some of the information on participant plans
against a primary disability in both the NDIA-run trial sites and the WA My Way
site.
2.33
The top four primary disabilities listed in a total of 17 303 NDIA
approved plans are: Autism (5 387 plans at 31 per cent), Intellectual
disability (2 736 plans at
16 per cent), Other Neurological (1 401 plans at 8 per cent) and Developmental
delay (1 395 at 8 per cent).
2.34
Table 2.3 provides plan numbers by state and territory. In terms of the
spread of particular disabilities across jurisdiction, South Australia has the
highest proportion of participants with autism and related disorders; it also
has a high proportion with developmental and global developmental delay (23 per
cent combined). While autism and developmental delay dominate the disabilities
overall, the Northern Territory disabilities focus on Other Neurological (21 per
cent), Other Physical (18 per cent) and Intellectual Disability (18 per cent).
Table 2.3. NDIA – Participant plans by primary disability support category
Primary Disability (%)
|
NSW
|
SA
|
TAS
|
VIC
|
ACT
|
NT
|
WA
|
Total
|
#Plans
|
Autism and Related Disorders
|
23
|
49
|
30
|
22
|
25
|
3
|
40
|
31
|
5,397
|
Cerebral Palsy
|
5
|
3
|
7
|
4
|
6
|
11
|
6
|
5
|
793
|
Deafness/Hearing Loss
|
3
|
3
|
0
|
1
|
2
|
0
|
1
|
2
|
358
|
Developmental Delay
|
4
|
13
|
2
|
7
|
19
|
3
|
1
|
8
|
1,395
|
Down Syndrome
|
4
|
2
|
7
|
4
|
4
|
3
|
5
|
4
|
666
|
Global Developmental Delay
|
3
|
10
|
2
|
3
|
5
|
5
|
6
|
5
|
853
|
Intellectual Disability
|
20
|
2
|
36
|
22
|
14
|
18
|
17
|
16
|
2,736
|
Multiple Sclerosis
|
2
|
0
|
0
|
3
|
2
|
2
|
3
|
2
|
285
|
Schizophrenia
|
6
|
0
|
1
|
6
|
1
|
5
|
1
|
3
|
558
|
Other Intellectual/learning
|
5
|
4
|
6
|
5
|
5
|
5
|
6
|
5
|
869
|
Other Neurological
|
13
|
2
|
5
|
10
|
6
|
21
|
8
|
8
|
1,401
|
Other Physical
|
4
|
2
|
2
|
3
|
5
|
18
|
4
|
3
|
566
|
Other Psychiatric
|
3
|
0
|
1
|
8
|
2
|
0
|
0
|
3
|
532
|
Other Sensory/Speech
|
5
|
9
|
1
|
3
|
5
|
5
|
3
|
5
|
894
|
Total
|
4,605
|
4,660
|
959
|
4,392
|
1,427
|
61
|
1,199
|
100%
|
17,303
|
Source: National Disability
Insurance Agency, Report on the sustainability of the scheme, 1 July
2013 – 30 June 2015, July 2015, p.29, p. 51.
Table 2.4. My Way – Participant plans by primary disability support
category
Primary disability
|
%
|
#Plans
|
CALD
|
ATSI
|
Male
|
Female
|
Acquired brain injury*
|
3%
|
26
|
0
|
0
|
16
|
10
|
Autism
|
19%
|
151
|
3
|
6
|
120
|
31
|
Deaf/blind
|
0%
|
3
|
0
|
0
|
0
|
3
|
Developmental delay
|
3%
|
22
|
1
|
1
|
16
|
6
|
Hearing
|
1%
|
7
|
0
|
0
|
4
|
3
|
Intellectual disability
|
34%
|
268
|
3
|
15
|
155
|
113
|
Neurological
|
10%
|
75
|
2
|
2
|
30
|
45
|
Other
|
0%
|
1
|
0
|
0
|
0
|
1
|
Physical
|
14%
|
108
|
0
|
4
|
53
|
55
|
Psychiatric/psychosocial disorders
|
12%
|
92
|
1
|
1
|
38
|
54
|
Learning/attention deficit disorder
|
0%
|
1
|
0
|
0
|
1
|
0
|
Vision
|
3%
|
23
|
0
|
0
|
10
|
13
|
Total
|
100%
|
777
|
10
|
29
|
443
|
334
|
Source: Disability Services
Commission, Quarterly Report to the Commonwealth Government, 1 April
2015 to 30 June 2015 (fourth quarterly report), p. 6, p.15. * Comparable data
on acquired brain injury is not published in NDIA reports.
2.35
In Table 2.4, of the 777 approved plans in the WA My Way site, the top
four primary disabilities listed are: Intellectual disability (268 plans at 34
per cent), Autism (151 plans at 19 per cent), Physical (108 plans at 14 per
cent) and Psychiatric/psychosocial disorders (92 at 12 per cent).
Committed supports
2.36
Overall, $952.8 million has been committed for participant support
costs. The NDIA Scheme Actuary notes that these 'support costs are mostly
allocated to a small proportion of high-cost participants'. This group consists
of more than 1600 participants representing just 10 per cent of total
participant numbers that have plans worth more than $100 000. These
participants' plans account for 47 per cent of the total committed supports—$148.2
million.[16]
2.37
The NDIA's quarterly report notes
a slightly higher percentile for those with plans over $100 000:
...the majority of participants have annualised package costs
of between $5,001 and $30,000 (64%) and few participants have high cost plans
of over $100,000 (10%). Of the 17,155 active participants with approved plans,
71% have an annualised package cost of less than $30,000. This group accounts
for only 26% of annualised committed funding. Conversely, 10% of participants
have an annualised package cost over $100,000 and these participants account
for 49% of total committed supports.[17]
Figure 2.1: Distribution of annualised support costs
2.38
Figure 2.1 displays the distribution of the active plans in the NDIA run
sites. The committee notes that even with the significant skew, as mentioned
above in term of concentration of funds, the average annualised package cost
across all trial sites is approximately $38 400. The NDIA goes on to note that if
the large residential centres, Stockton and Colanda, are excluded from this
calculation, then the average annualised package cost comes down to $33 600.
2.39
The NDIA eighth quarterly report indicated that despite average package
costs being higher than expected, the overall cost of the scheme is in line
with expectations. The NDIA state that the higher costs are due to the lower
number of low cost participants entering the scheme. However, the number of
higher cost participants and medium cost participants are in line with
expectations.[18]
2.40
The quarterly report also stated that actual package costs differ from
expected package costs:
The distribution of the cost of support packages differs from
expected across all trial sites. In particular, a higher proportion of low cost
participants were expected compared with actual experience, and there are a
higher proportion of participants receiving mid-range packages than expected.[19]
Trial sites commenced 1 July 2014
2.41
This section presents an overview of each of three trial sites—ACT,
Western Australia and the Barkley—that all commenced operations on 1 July 2014.
The ACT trial site
2.42
The committee held public hearings at Parliament House in Canberra on
27 March 2015. The committee took evidence from 17 participants and carers and 11 individuals
representing service providers. In the afternoon, the committee heard from the
ACT Government's Disability ACT and ACT NDIA officials. After the main hearing
the committee held an Advocacy roundtable taking evidence from nine
organisations.
2.43
The ACT will be the first jurisdiction as a whole to roll out the NDIS.
Other jurisdictions are entering by designated areas and/or selected
categories. For the ACT this transition will involve approximately 5000 people.
Transition arrangements
2.44
People with disability in the ACT will gradually transition to the
Scheme over a two year period. Table 2.5 on the following page provides a
schematic of the transition arrangements for the ACT trial site. The intake
for the trial site was agreed to be in 'ages and stages', which involves
transitioning clients by 'specific age cohorts determined by date of birth or
by academic year for children and young people of school age concurrently'.[20]
Table 2.5: Transition arrangements in the ACT trial site for 2014-15
|
1st Quarter
|
2nd Quarter
|
3rd Quarter
|
4th Quarter
|
Age Based
Those born:
|
1 July 1949 to
30 June 1950
|
1 July 1950 to
30 June 1951
|
1 July 1951 to
30 June 1954
|
1 July 1954 to 30 June 1955
|
School Aged and Infants
Those born:
|
1 July 2012 to 30 June 2014
and 2008–2014 School Leavers
|
1 July 2010 to
30 June 2012, School Leavers, and any children not
expected to commence school in 2015–16
|
School years: 7 to 12
|
School years: Kindergarten to
6
|
Group Home Accommodation Youngest resident born:
|
1 July 1992 or later
|
23 August 1989 to
30 June 1992
|
24 October 1983 to
22 August 1989
|
29 October 1981 to 23 October 1983
|
Source: Bilateral Agreement
between the Commonwealth and Australian Capital Territory, Appendix C, p. 12.
2.45
The intakes for 2015-16 and 2016-17 follow a similar progressive pattern
to transition all eligible people into the scheme. All participants are
scheduled to transition into the scheme by the end of the first quarter of
2016-17.[21]
2.46
The committee is aware of the opportunities, benefits and challenges of a
geographically and demographically smaller trial site and of transitioning an
entire jurisdiction into the scheme during the trial period.
Table 2.6: Key statistics of the new trial sites (after 1 year)
|
ACT
|
Barkly (NT)
|
Perth Hills
|
MyWay (WA)
|
Average annualised committed cost of individual packages ($)
|
45,361
|
50,327
|
34,894
|
26,014
|
Number of participants in bilateral agreement, 30 June 2015
|
1,537
|
103
|
1,642
|
1,404
|
Number of participants with approved plans, 30 June 2015
|
1,427
|
61
|
1,199
|
688
|
Access requests
|
2,314
|
79
|
1,576
|
n/a
|
Accepted as eligible
|
2,037
|
68
|
1,396
|
777
|
Ineligible
|
143
|
6
|
106
|
n/a
|
Other
|
134
|
5
|
74
|
n/a
|
Average days from access request to plan approval in 2014-15
|
58
|
36
|
31
|
53
|
Review of decisions (internal)
|
31
|
0
|
11
|
0
|
Appeals to the Administrative Appeal Tribunal (AAT)
|
2
|
0
|
2
|
n/a
|
Participants accessing mainstream services (% of total)
|
87
|
82
|
66
|
n/a
|
Source: National Disability
Insurance Agency, Quarterly Report to COAG Disability Reform Council, 30
June 2015, pp 28, 40, 41, 49 and 55. WA Disability Services Commission, Quarterly
Report to the Commonwealth Government, 30 June 2015, pp 6 and 23.
Transition progress in the ACT trial
site[22]
2.47
As of 30 June 2015, 1427 people have approved individualised support
plans. The NDIA report that the average package cost is $45 361. Of these plans
48 per cent are managed by the NDIA, 41 per cent are managed as a combination
between the Agency and the individual or services provider(s), and importantly,
11 per cent are entirely self-managed. The total cost of committed supports for
participants to 30 June 2015 at the ACT trial site was $64 670 395.
2.48
There are 169 registered service providers in the ACT providing a range
of services that can be accessed through the NDIA's 'Find registered service
providers' web portal.[23]
The Western Australian trial sites
2.49
Western Australia is conducting two trials to assess the NDIS and MyWay
models in providing disability support—both commenced on 1 July 2014.
2.50
The NDIS trial site, located in the Perth Hills area, is managed by the
NDIA. It encompasses the Swan, Kalamunda and Mundaring local government areas.
2.51
While the WA NDIS MyWay trial site is managed by the WA Disability
Services Commission (DSC) and is located in the Lower South West area. The
Cockburn and Kwinana trial site joined the My Way trial on 1 July 2015.
2.52
The committee held a public hearing in Busselton on 8 April 2015. The
committee took evidence from 12 participants and carers and 16 individuals
representing service providers in Busselton.
2.53
On 9 April 2015, the committee held a public hearing in the Perth Hills taking
evidence from 7 participants and carers and 13 individuals representing
service providers.
Transition arrangements
2.54
This section provides brief details of the My Way transition
arrangements.
Table 2.7: WA NDIS My Way estimated participant population[24]
Year
|
2014-15
|
2015-16
|
Estimated Lower South West
participant population
|
1,404
|
1,418
|
Estimated Cockburn/Kwinana
participant population
|
0
|
2,715
|
Estimated total participant
population
|
1,404
|
4,133
|
2.55
The WA NDIS MyWay trial is governed by the National Partnership
Agreement on trial of My Way sites, an agreement between the Commonwealth and
Western Australian Governments. Table 2.7 above shows the estimated participant
population covered by the two initial NDIS MyWay trial sites once both are up
and running.
Table 2.8: Key statistics of the new
trial sites (after 1 year)
|
ACT
|
Barkly (NT)
|
Perth Hills
|
MyWay[25] (WA)
|
Average annualised committed cost of individual packages ($)
|
45,361
|
50,327
|
34,894
|
26,014
|
Number of participants in bilateral agreement, 30 June 2015
|
1,537
|
103
|
1,642
|
1,404
|
Number of participants with approved plans, 30 June 2015
|
1,427
|
61
|
1,199
|
688
|
Access requests
|
2,314
|
79
|
1,576
|
n/a
|
Accepted as eligible
|
2,037
|
68
|
1,396
|
777
|
Ineligible
|
143
|
6
|
106
|
n/a
|
Other
|
134
|
5
|
74
|
n/a
|
Average days from access request to plan approval in 2014-15
|
58
|
36
|
31
|
64
|
Review of decisions (internal)
|
31
|
0
|
11
|
0
|
Appeals to the Administrative Appeal Tribunal (AAT)
|
2
|
0
|
2
|
n/a
|
Participants accessing mainstream services (% of total)
|
87
|
82
|
66
|
n/a
|
Source:
National Disability Insurance Agency, Quarterly Report to COAG Disability
Reform Council, 30 June 2015, and WA Disability Services Commission, Quarterly
Report to the Commonwealth Government, 30 June 2015.
Transition progress in the WA trial sites[26]
2.56
An independent evaluation of both WA trial site models will take place
through the trial period. The evaluation will be overseen by the joint steering
committee managed out of the Department of the Prime Minister and Cabinet and will
provide an interim report in October 2015 and a final report in August 2016.[27]
2.57
The committee acknowledges that it is difficult to compare the two WA sites
and as such no direct comparison will be undertaken in this report other than
reporting the two sites key statistics and transition rates.
2.58
The Perth Hills trial site covers a smaller geographic area, is
metropolitan, and has a larger number of participants than the WA NDIS My Way
trial site. The Lower South West My Way trial site is building on an existing
system of local area coordinators, which in effect is a 'business as usual'
arrangement that links in with a state run system that has been in operation
for over twenty years.
2.59
As of 30 June 2015, the Perth Hills site had approved 1199 people for an
individualised support plan. The average package cost in the Perth Hills trial
site is $34 894.
2.60
Of these plans, 60 per cent are managed by the NDIA, 31 per cent are
managed as a combination between the Agency and the individual or services provider(s),
and 9 per cent are entirely self-managed.
2.61
The NDIA quarterly report does not provide a breakdown of the number of service
providers registered by state and territory so no details can be provided.
2.62
The total cost of committed supports for participants to 30 June 2015 at
NDIA Perth Hills trial site was $41 220 779.
Table 2.9: 2014-15 My Way participation figures and associated data
WA NDIS My Way trial
|
Total
|
Total committed plan costs
|
$17.9 million
|
Total number of individuals eligible for support
|
777
|
Total number of individuals with current plans (funded and no
funding requested)
|
688
|
Total number of current plans (with funding)
|
643
|
Total number of current plans (with no funding requested)
|
45
|
Total year to date payments for the period
|
$14 million
|
Average costs for total current plans (funded and no funding
requested)
|
$26,014
|
Average costs for current plans (with funding)
|
$27,834
|
Number of service providers operating in the trial site
|
36
|
Source: WA Disability Services Commission, Quarterly
Report to the Commonwealth Government, 30 June 2015, p. 6.
2.63
The average length of time for a plan to be approved has been 64 days
with an average package cost of $26 014 for (643 funded and 45 no funding
requested).
2.64
It was expected that DSC clients would phase into NDIS My Way from
1 July 2014 in the Lower South West trial site. According to the latest
DSC My Way quarterly report, a total of 688 individuals have now received
plans. Of these, 374 have requested access since the scheme began, the rest
were transferred directly into the scheme on 1 July 2014. Other participants
will be phased in on a quarterly basis as outlined in Table 2.7.
2.65
Of these plans, 29 per cent are managed by a service provider, 36 per
cent are managed by a combination of the DSC and the individual or services provider(s),
and 35 per cent are entirely self-managed.
2.66
There are 36 registered service providers registered in the My Way trial
site; 72 per cent of registered providers in the trial site are operating in
the state only, with 28 per cent having a national presence. The total cost of
NDIS funded supports to 30 June 2015 was $17.9 million.
2.67
Table 2.9 shows among other key findings that the actual numbers are
below the anticipated National Partnership Agreement participant numbers.
2.68
At the end of the fourth quarter the 688 participant numbers in the WA
NDIS My Way trial are considerably lower than the expected at 1404—see Table
2.8 for expected bilateral numbers.
2.69
While noting that the forecasts were in their very early stages, Mr
Greenway, one of the representatives from the WA NDIS My Way Scheme Actuary
TaylorFry, told the committee in June that:
We will be revisiting the forecasts soon...We are also
undertaking some
in-depth analysis to look into why the numbers of participants are lower than
were expected. [28]
2.70
Mr Greenway had previously provided greater detail to the above comments
in the WA NDIS My Way fourth quarterly report:
As at 30 June 2015, there are 35% fewer individuals in the
trial than expected. The disparity with expectations is due partly to the slow
emergence of individuals with psychosocial disability and individuals that
qualify for early intervention. We anticipate that participation will move
closer to expectations with the continued emergence of these individuals, but
we do not anticipate that the ultimate number of individuals will reach initial
expectations for the Lower South West. [29]
2.71
However, Mr Greenway did state to the committee that:
Using the forecasts as a basis for sustainability, if the forecasts
are what was expected and if that is the level of sustainability that you need,
then certainly this trial is on track in terms of sustainability.[30]
2.72
A lower than expected figure is also a feature of the NDIA run Perth
Hills trial site where transition numbers against the agreed bilateral numbers
are also low at approximately 73 per cent completion.
2.73
The committee notes the experiences of participants and providers at
both trial sites, and the long history of the My Way model which effectively began
in 1988. At its hearings in WA, the committee heard many positive stories of
how both trials were striving and succeeding in changing people's lives.
The Barkly trial site
2.74
Members of the committee visited the Barkly trial site headquarters at
Tennant Creek on 20 July 2015 and met with 11 local participants, carers and
the staff of the NDIA office, more detail is at paragraph 2.19. The committee
held a public hearing in Darwin on 21 July 2015, where it took evidence from 10
individuals representing service providers in the Northern Territory.
2.75
The Barkly trial site encompasses the Barkly Regional Council local
government area of the Northern Territory. It is the largest trial site
covering approximately 323 514 km—the region is very sparsely populated.2 The
estimated population of Barkly is 8056, which includes a population of 3,560 in
Tennant Creek—the largest concentration of residents. This equates
to two people per 100 square kilometres.[31]
Transition arrangements
2.76
Residents under the age of 65 years with permanent and significant
disability who meet the access requirements are gradually entering the Scheme which
commenced from 1 July 2014. Existing service users and new
participants will enter the Scheme progressively on a community by community
basis as NDIA staff visit towns and remote communities. The Barkly NDIA office
is located in Tennant Creek.
Table 2.10: Key statistics of the new
trial sites (after 1 year)
|
ACT
|
Barkly (NT)
|
Perth Hills
|
MyWay (WA)
|
Average annualised committed cost of individual packages ($)
|
45,361
|
50,327
|
34,894
|
26,014
|
Number of participants in bilateral agreement, 30 June 2015
|
1,537
|
103
|
1,642
|
1,404
|
Number of participants with approved plans, 30 June 2015
|
1,427
|
61
|
1,199
|
688
|
Access requests
|
2,314
|
79
|
1,576
|
n/a
|
Accepted as eligible
|
2,037
|
68
|
1,396
|
777
|
Ineligible
|
143
|
6
|
106
|
n/a
|
Other
|
134
|
5
|
74
|
n/a
|
Average days from access request to plan approval in 2014-15
|
58
|
36
|
31
|
53
|
Review of decisions (internal)
|
31
|
0
|
11
|
0
|
Appeals to the Administrative Appeal Tribunal (AAT)
|
2
|
0
|
2
|
n/a
|
Participants accessing mainstream services (% of total)
|
87
|
82
|
66
|
n/a
|
Source:
National Disability Insurance Agency, Quarterly Report to COAG Disability
Reform Council, 30 June 2015, and the WA Disability Services Commission, Quarterly
Report to the Commonwealth Government, 30 June 2015,
2.77
The bilateral agreement notes that the order in which specific
communities will be assisted and the timing of assistance to Tennant Creek
participants will be settled in discussions between the NT Government and the
NDIA. Table 2.11 shows the bilateral agreement estimates of participant
population covered by the Barkly trial site. Table 2.12 shows the estimated
total cost of NDIS funded supports in line with the agreed participation
population as shown in Table 2.11.
2.78
The bilateral planned intake of participants states that:
- by 30 September 2014 current disability and mental health clients receiving
NT or Commonwealth services will be assisted to access the Scheme on a
community by community basis; and
-
new clients not currently receiving services will be assisted to access
the Scheme as their community phases in.[32]
2.79
All participants are scheduled to transition into the scheme by July
2019.
Table 2.11 Northern Territory NDIS bilateral agreement participant numbers
Year:
|
2014-15
|
2015-16
|
Estimated Northern Territory
participant population
|
103
|
104
|
Table 2.12 Cost of Northern Territory NDIS supports
Year:
|
2014-15
|
2015-16
|
Estimated
total cost of NDIS funded supports
|
$3.3 million
|
$4.0 million
|
Transition progress in the Barkly trial site[33]
2.80
As of 30 June 2015, 61 people in the NT have approved individualised
support plans. The average package cost in the Barkly trial site is $50 327.
2.81
Of these plans, 93 per cent are managed by the NDIA, the remainder are
managed in a combination of both the agency and the participant. No plans are
self-managed.
2.82
The NDIA quarterly report does not provide a breakdown of the number of
service providers registered by state and territory so no details can be
provided.
2.83
The total cost of committed supports for participants to 30 June 2015 at
the Barkly trial site was $3 061 377.
Challenges in the Barkly trial site
2.84
As outlined earlier, it is anticipated that the Barkly trial will
provide valuable experience and understanding in delivering the NDIS in remote
areas, which will inform the roll-out across the rest of the NT and other
remote parts of Australia. Apart from dealing with the direct challenge of the
high rate of disability among Indigenous Australians compared to the general
Australian population, the implementation of the Barkly trial presents a number
of specific challenges:
-
low numbers of Indigenous Australians with disability accessing
the disability service system—a contributing factor is the reluctance of
Indigenous people with disability to identify as a person with disability. This
presents a significant barrier to the successful implementation of the NDIS in
this region;
-
experience of Indigenous Australians when using services—a lack
of confidence in dealing with, and a mistrust of, government agencies and
service providers;
-
differences in cultural backgrounds and understanding between
service providers and Indigenous Australians—this can form an impediment to
effective delivery of support services; and
-
access to services—lack of available and appropriate services due
to the remote location.
2.85
The fundamental principle of the NDIS is individual choice and control.
Enabling Indigenous Australians to exercise such choice and control may be
difficult where the absence of service providers in remote areas precludes
meaningful choice.
2.86
The evidence that the committee heard in Darwin regarding the Barkly
trial confirms the incredible difficultly in delivering high quality services
to regional and remote areas of Australia and as such represents one of the biggest
challenges to the Scheme.
Committee view
2.87
This chapter has outlined the progress of the trial sites in 2014-15. Issues
raised in the trial site hearings will be discussed in later chapters. This
includes issues for participants, providers and market development and assistance
which were raised during hearings in multiple trial sites.
2.88
The committee thanks all who have contributed to the committee’s work. The
committee appreciates the time and effort that people have put in to making
submissions and giving evidence at public hearings.
2.89
The committee acknowledges the importance of trial sites in showing where
the Scheme works well and how it could be improved. The committee notes that
the trial sites are not all identical and have varying issues that are impacted
by factors including the geographic and demographic size of the trial site, the
cohort in transition and the length of the trial period so far.
2.90
The committee continues to find trial site visits an informative and
valuable undertaking. Accordingly, the committee intends to conduct further
visits to both the existing and new trial sites in the coming year noting that
the full roll out of the Scheme will commence in mid-2016.
Navigation: Previous Page | Contents | Next Page